Answering: “In the first part of Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams identify many dependencies. This makes it hard for them to choose the work they could pull into their individual teams for the next Sprint. No matter how they reorganize the Product Backlog items, they continually find more or new dependencies. There are especially two teams that have a lot of dependent work. What would you recommend to the two teams that are continually dependent on each other to help them manage their work?”

Managing Dependencies Between Scrum Teams

In a Nexus with multiple Scrum Teams, managing dependencies is crucial for smooth Sprint execution and achieving the Nexus Sprint Goal. Specific strategies and practices can help teams effectively manage their dependencies and ensure efficient collaboration.

Exam Question

Scenario C: Dependencies and Product Backlog Items

In the first part of Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams identify many dependencies. This makes it hard for them to choose the work they could pull into their individual teams for the next Sprint. No matter how they reorganize the Product Backlog items, they continually find more or new dependencies. There are especially two teams that have a lot of dependent work.
What would you recommend to the two teams that are continually dependent on each other to help them manage their work?

(choose the best answer)
A. Merge the two Scrum Teams together.
B. The Nexus Integration Team should be responsible for integrating the work of these two Scrum Teams.
C. Reorganize these two Scrum Teams so that one is responsible for development and one is responsible for integration.
D. Ensure the appropriate representatives from both teams are present during Cross-Team Refinement.

Correct Answer

D. Ensure the appropriate representatives from both teams are present during Cross-Team Refinement.

Explanation

Correct Answer

D. Ensure the appropriate representatives from both teams are present during Cross-Team Refinement:
Having representatives from both teams present during Cross-Team Refinement sessions is crucial for identifying and addressing dependencies early. This collaboration allows both teams to plan their work with a clear understanding of interdependencies, fostering better coordination and reducing potential bottlenecks during the Sprint.

Why the Other Options Are Less Effective

A. Merge the two Scrum Teams together:
Merging two teams might seem like a solution, but it can lead to a larger team size, which can be less effective and reduce overall agility. It might also disrupt team dynamics and roles.

B. The Nexus Integration Team should be responsible for integrating the work of these two Scrum Teams:
While the Nexus Integration Team plays a critical role in integration, making them solely responsible for the dependencies between two specific teams could lead to bottlenecks and overload. Integration should be a collaborative effort involving all relevant teams.

C. Reorganize these two Scrum Teams so that one is responsible for development and one is responsible for integration:
Splitting responsibilities in this manner goes against the principles of Scrum, where each team should be cross-functional and capable of delivering increments of value independently.

Benefits of Cross-Team Refinement

  • Early Identification of Dependencies: Ensures that dependencies are identified and addressed before they become bottlenecks.
  • Improved Coordination: Facilitates better planning and coordination between teams, leading to smoother Sprint execution.
  • Enhanced Collaboration: Encourages teams to work together and understand each other’s constraints and dependencies.

Relevance to the SPS Exam

Understanding the importance of effective dependency management and the role of Cross-Team Refinement is crucial for the SPS exam. It demonstrates the ability to apply scaled Scrum practices to ensure cohesive and efficient team collaboration in a multi-team environment.

Key Takeaways

  • Cross-Team Refinement is essential for early identification and management of dependencies.
  • Effective collaboration between teams improves planning and reduces potential bottlenecks.
  • Proper dependency management is critical for achieving the Nexus Sprint Goal.

Conclusion

Ensuring that representatives from dependent teams participate in Cross-Team Refinement sessions helps manage dependencies effectively, leading to better coordination and successful Sprint outcomes. For more information on preparing for the SPS exam, visit our Scaled Professional Scrum SPS™ Exam Prep.

Table of Contents

Sign up for more exam tips and discounts



How To Pass SPS Exam on the First Try
ScrumPrep

SPS Exam Guide

The Scaled Professional Scrum (SPS) exam is a challenging certification that validates one’s knowledge and expertise in scaling Scrum. It is a globally recognized certification that offers numerous benefits to individuals and organizations. However, passing the exam is not easy and requires adequate preparation and dedication. In this article, we will provide you with tips and strategies on how to pass the SPS exam and earn your certification. Table of Contents Understanding the SPS Exam Purpose and Structure The SPS exam is designed to assess your knowledge of the Nexus Framework and your ability to apply Scrum in large-scale environments. The exam consists of multiple-choice questions, which you must complete within a specified time. A passing score earns you the

Read More »

Related Products

LIMITED TIME SALE!
SPS Practice Tests - ScrumPrep
Master the art of scaling product development with multiple Scrum Teams working together. Easily pass the exam and become a certified SPS professional.
  • 182 SPS™ exam sample questions
  • Five complete exams with up to 40 questions each
  • Real exam mode with unlimited question combinations
  • Questions developed by experienced Scrum exam experts
  • Updated to the current SPS™ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here