Answering: “What happens during Sprint 0?”

Table of Contents

Understanding Sprint 0 in Scrum

The concept of “Sprint 0” is often discussed in Agile and Scrum practices, but it is not officially recognized in the Scrum framework. This question addresses the confusion around Sprint 0 and what activities are sometimes associated with it.

Exam Question

What happens during Sprint 0?
(choose the best answer)
A. There is no such thing as Sprint 0.
B. Requirements gathering, version control setup, and continuous integration setup.
C. Establish base system architecture and design, install version control and continuous integration setup.
D. Overall planning, base system architecture, base design, version control and continuous integration setup.

Correct Answer

A. There is no such thing as Sprint 0.

Explanation

Correct Answer

A. There is no such thing as Sprint 0:
In the official Scrum framework, there is no concept of a “Sprint 0.” Scrum starts with the first Sprint, during which a usable Increment is produced. All the necessary activities, such as setting up the environment, architecture, and tools, should be done either before starting the first Sprint or as part of the first Sprint itself. The idea of Sprint 0 is sometimes used in organizations to describe a preparatory phase, but it is not a part of Scrum.

Why the Other Options Are Incorrect

B. Requirements gathering, version control setup, and continuous integration setup:
While these activities are important, they are not part of an official Sprint 0 in Scrum. These tasks can be done before the first Sprint begins or as part of the first Sprint, but there is no formal “Sprint 0” in Scrum.

C. Establish base system architecture and design, install version control and continuous integration setup:
Similar to option B, these activities might be necessary for a project, but they are not officially recognized as part of a “Sprint 0” in Scrum. These tasks can be integrated into the first Sprint if needed.

D. Overall planning, base system architecture, base design, version control and continuous integration setup:
Again, these activities are essential but should be completed either before the first Sprint or during the first Sprint. There is no official “Sprint 0” in Scrum to handle these activities.

Relevance to the PSD Exam

Understanding that there is no Sprint 0 in Scrum is crucial for the PSD exam. This knowledge reinforces the importance of adhering to the Scrum framework and recognizing that preparation activities should be handled before or as part of the first Sprint.

Key Takeaways

  • No Sprint 0: Scrum does not recognize a Sprint 0; all necessary activities should be managed either before the first Sprint or within the first Sprint.
  • Adhering to Scrum: It’s important to follow the official Scrum framework and avoid introducing unofficial phases like Sprint 0.

Conclusion

In Scrum, there is no concept of Sprint 0. All necessary setup activities should be done before or during the first Sprint, and the focus should be on delivering a usable Increment right from the start. For more information on preparing for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.