Answering: “When is it most appropriate for a Scrum Team to change the Definition of Done?”

Adjusting the Definition of Done in Scrum

The Definition of Done (DoD) is a crucial component in Scrum, ensuring that all team members have a shared understanding of what it means for work to be considered complete. Adjusting the DoD is essential to improving quality and adapting to changes. This article explores a specific exam question about the most appropriate time for a Scrum Team to change the Definition of Done, providing detailed explanations and insights relevant to the PSM I exam.

Exam Question

When is it most appropriate for a Scrum Team to change the Definition of Done? (choose the best answer)

  • A. During the Sprint Retrospective.
  • B. During Sprint Planning.
  • C. During Product Backlog refinement.
  • D. Prior to starting a new project.

Correct Answer

A. During the Sprint Retrospective.

Explanation

Correct Answer

A. During the Sprint Retrospective: The Sprint Retrospective is the most appropriate time to change the Definition of Done. This event is dedicated to reflecting on the past Sprint and identifying areas for improvement. Adjusting the DoD during this time ensures that any changes are based on recent experiences and learnings, and the entire team can agree on and understand the new standards before the next Sprint begins.

Incorrect Answers

B. During Sprint Planning: While Sprint Planning is focused on defining what can be delivered in the upcoming Sprint and how to achieve it, it is not the ideal time to change the Definition of Done. Changes to the DoD should be made after careful reflection and discussion, which is best suited for the Sprint Retrospective.

C. During Product Backlog refinement: Product Backlog refinement is an ongoing process to keep the Product Backlog items detailed and ready for future Sprints. It is not the time to make fundamental changes to the Definition of Done, which requires a more focused and reflective discussion.

D. Prior to starting a new project: While it might seem logical to define or refine the Definition of Done before starting a new project, in Scrum, adjustments to the DoD should be made based on the team’s ongoing experiences and continuous improvement mindset. The Sprint Retrospective provides this opportunity.

Responsibilities in Scrum

  • Product Owner: The Product Owner collaborates with the team during the Sprint Retrospective to provide insights and feedback that may influence changes to the Definition of Done, ensuring it aligns with the product vision and goals.
  • Scrum Master: The Scrum Master facilitates the Sprint Retrospective, guiding the team through the process of reflecting on their work and making necessary improvements, including changes to the Definition of Done.
  • Developers: Developers participate actively in the Sprint Retrospective, discussing their experiences and suggesting changes to the Definition of Done to improve quality and efficiency.

Relevance to the PSM I Exam

Understanding when and how to adjust the Definition of Done is crucial for the PSM I exam. It demonstrates a comprehensive knowledge of Scrum events and the continuous improvement process. Mastering these concepts is essential for facilitating effective Scrum practices and ensuring that all team members have a clear understanding of what is required to deliver a Done Increment.

Key Takeaways

  • The Sprint Retrospective is the most appropriate time to change the Definition of Done.
  • Adjustments to the Definition of Done should be based on reflection and team consensus.
  • Each Scrum role has specific responsibilities in the process of refining the Definition of Done.

Conclusion

Adjusting the Definition of Done during the Sprint Retrospective ensures that changes are well-considered and based on recent experiences. This practice fosters continuous improvement and enhances the quality of the product. Understanding when to adjust the DoD is essential for effective Scrum implementation and success in the PSM I exam. For comprehensive preparation and practice exams, check out PSM I Exam Prep to enhance your understanding and application of Scrum principles.

Table of Contents

Sign up for more exam tips and discounts



How To Pass PSM I Exam on the First Try
ScrumPrep

PSM I Exam Guide

The Professional Scrum Master I (PSM I) certification is one of the most popular certifications for professionals who want to demonstrate their understanding of the Scrum framework and their ability to apply Scrum in real-world situations. The certification is offered by Scrum.org, a leading global provider of Scrum training and

Read More »

Related Products

LIMITED TIME SALE!
PSM I Practice Tests - ScrumPrep
Power-packed PSM I practice questions and exams will transform your Scrum knowledge and help you pass the PSM I exam easily.
  • 480 PSM Iâ„¢ exam questions
  • Six complete exams with 80 questions each
  • Real exam mode with unlimited question combinations
  • Questions developed by experienced Scrum exam experts
  • Updated to the current PSM Iâ„¢ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here