Answering: “When is the Sprint Backlog created?”

Table of Contents

Creation of the Sprint Backlog in Scrum

The Sprint Backlog is a crucial artifact in Scrum, representing the work selected for the Sprint and the plan for delivering it.

Exam Question

When is the Sprint Backlog created?
(choose the best answer)
A. Prior to the Sprint Planning event.
B. During the Sprint.
C. At the beginning of the project.
D. During the Sprint Planning event.

Correct Answer

D. During the Sprint Planning event.

Explanation

Correct Answer

D. During the Sprint Planning event:
The Sprint Backlog is created during the Sprint Planning event. This event marks the beginning of the Sprint, where the Scrum Team collaborates to select Product Backlog items for the Sprint and create a plan to deliver them. The Sprint Backlog includes these selected items along with a detailed plan on how the work will be completed.

Why the Other Options Are Less Effective

A. Prior to the Sprint Planning event:
The Sprint Backlog cannot be created before the Sprint Planning event because it is during this event that the team decides what work will be done in the upcoming Sprint.

B. During the Sprint:
The Sprint Backlog is created at the start of the Sprint during the Sprint Planning event. While it can be adjusted during the Sprint as needed, its initial creation happens during Sprint Planning.

C. At the beginning of the project:
The Sprint Backlog is specific to each Sprint and is created at the start of each Sprint during the Sprint Planning event. It is not created at the beginning of the project.

Importance of the Sprint Planning Event

  • Planning and Commitment: The Sprint Planning event allows the Scrum Team to collectively decide what work they can commit to completing in the upcoming Sprint.
  • Alignment: It ensures that everyone on the team is aligned on the goals and plan for the Sprint, fostering collaboration and shared understanding.
  • Adaptability: Creating the Sprint Backlog at the start of each Sprint allows the team to adapt to changing priorities and information, ensuring that they are always working on the most valuable tasks.

Effective Practices for Sprint Planning

  • Collaborative Planning: Engage all team members in the planning process to leverage their collective knowledge and expertise.
  • Clear Goals: Define clear and achievable Sprint Goals to guide the team’s work during the Sprint.
  • Detailed Planning: Break down selected Product Backlog items into actionable tasks to create a clear plan for the Sprint.

Relevance to the PSU I Exam

Understanding when the Sprint Backlog is created is crucial for the PSU I exam. It demonstrates knowledge of Scrum events, artifacts, and the importance of proper planning in achieving successful Sprints.

Key Takeaways

  • The Sprint Backlog is created during the Sprint Planning event.
  • This event allows the team to select Product Backlog items and create a plan for the Sprint.
  • Effective Sprint Planning ensures alignment, clear goals, and detailed planning.

Conclusion

The Sprint Backlog is created during the Sprint Planning event, where the Scrum Team collaborates to select and plan the work for the upcoming Sprint. This ensures that the team is aligned and has a clear plan to achieve the Sprint Goal. For more information on preparing for the PSU I exam, visit our Professional Scrum with UX PSU Iâ„¢ Exam Prep.