Answering: “Which statement best describes the Sprint Backlog as the output of the Sprint Planning?”

Table of Contents

Understanding the Sprint Backlog in Scrum

The Sprint Backlog is a crucial artifact in Scrum, serving as a dynamic plan for the Scrum Team during a Sprint. This article delves into the nature of the Sprint Backlog, its purpose, and the roles associated with it within the Scrum framework.

Exam Question

Which statement best describes the Sprint Backlog as the output of the Sprint Planning?
(choose the best answer)
A. It is a complete list of all work to be done in a Sprint.
B. Each task is estimated in hours.
C. It is the Scrum Team’s plan for the Sprint.
D. Every item has a designated owner.
E. It is ordered by the Product Owner.

Correct Answer

C. It is the Scrum Team’s plan for the Sprint.

Explanation

Correct Answer

C. It is the Scrum Team’s plan for the Sprint:
The Sprint Backlog is essentially the plan created by the Scrum Team during Sprint Planning. It includes the set of Product Backlog items selected for the Sprint, along with a plan for delivering the product Increment and achieving the Sprint Goal.

Incorrect Answers

A. It is a complete list of all work to be done in a Sprint: The Sprint Backlog is a forecast of work the Scrum Team plans to do during the Sprint, but it is not necessarily a complete list. The work may evolve as more is learned throughout the Sprint.

B. Each task is estimated in hours: While some teams may choose to estimate tasks in hours, it is not a requirement for the Sprint Backlog. The focus is on delivering valuable increments rather than tracking individual hours.

D. Every item has a designated owner: In Scrum, the work is collectively owned by the Scrum Team. Individual ownership of items is discouraged to promote collaboration and shared responsibility.

E. It is ordered by the Product Owner: The Sprint Backlog is created and managed by the Scrum Team, not the Product Owner. The Product Owner orders the Product Backlog, but the Sprint Backlog is the domain of the Developers.

Responsibilities in Scrum

  • Product Owner: The Product Owner is responsible for ordering the Product Backlog to maximize value. They do not order the Sprint Backlog but ensure that the selected Product Backlog items align with the product goals.
  • Scrum Master: The Scrum Master facilitates the Sprint Planning meeting and helps the Scrum Team understand the purpose and content of the Sprint Backlog. They ensure that the Scrum Team adheres to Scrum practices and helps remove any impediments.
  • Developers: The Developers create the Sprint Backlog during the Sprint Planning meeting. They are responsible for estimating, planning, and managing their work to achieve the Sprint Goal.

Relevance to the PSPO I Exam

Understanding the nature and purpose of the Sprint Backlog is essential for the PSPO I exam. This knowledge ensures that candidates can effectively support the Scrum Team in planning and managing their work during a Sprint, leading to successful product delivery.

Key Takeaways

  • The Sprint Backlog is the Scrum Team’s plan for the Sprint.
  • It includes selected Product Backlog items and a plan for delivering the product Increment.
  • The Sprint Backlog is created and managed by the Developers.
  • The Product Owner orders the Product Backlog, not the Sprint Backlog.
  • The Sprint Backlog may evolve as more is learned during the Sprint.

Conclusion

The Sprint Backlog is a fundamental component of the Scrum framework, guiding the Scrum Team’s work during a Sprint. Understanding its purpose and management is crucial for successful Scrum implementation. For more information on preparing for the PSPO I exam, visit the PSPO I Exam Prep.