Answering: “Who should be present during Product Backlog refinement?”

Table of Contents

Understanding Who Should Attend Product Backlog Refinement

Product Backlog refinement is an ongoing process in Scrum where the Product Owner and Developers collaborate to ensure that the Product Backlog items are well understood, appropriately sized, and ready for future Sprints. It’s important to know who should be involved in this process to maximize its effectiveness.

Exam Question

Who should be present during Product Backlog refinement?
(choose all that apply)
A. Only the most senior developers from the Scrum Team.
B. The Product Owner.
C. The stakeholders.
D. The external business analysts that have prepared the functional details.
E. The Developers.
F. The integration architects from the release department.

Correct Answers

B. The Product Owner.
E. The Developers.

Explanation

Correct Answers

B. The Product Owner:
The Product Owner is responsible for the Product Backlog and must be involved in refinement to ensure that the items are well understood, prioritized (ordered), and aligned with the product goals.

E. The Developers:
The Developers are responsible for delivering the Increment, and their involvement in refinement ensures that they have a clear understanding of the Product Backlog items, can estimate the work, and can address any technical concerns or dependencies.

Why the Other Options Are Less Appropriate

A. Only the most senior developers from the Scrum Team:
All Developers can be involved in refinement, not just the most senior ones. Refinement is a collaborative process where the entire team can contribute to understanding and preparing the Product Backlog items.

C. The stakeholders:
While stakeholders may provide valuable input, they are not typically present during the refinement sessions. The Product Owner represents the stakeholders’ interests during refinement.

D. The external business analysts that have prepared the functional details:
External business analysts are not typically part of the Scrum Team and therefore do not usually participate in Product Backlog refinement. The Scrum Team, especially the Product Owner, handles this responsibility.

F. The integration architects from the release department:
Integration architects are not usually part of the Scrum Team and are not required to be present during refinement. The Scrum Team focuses on the technical and functional aspects of the items to prepare them for implementation.

Relevance to the PSD Exam

Understanding who should participate in Product Backlog refinement is essential for the PSD exam. It emphasizes the importance of collaboration between the Product Owner and Developers and the role of refinement in preparing work for future Sprints.

Key Takeaways

  • Product Backlog refinement is a collaborative process involving the Product Owner and Developers.
  • Stakeholders and external parties do not typically participate in refinement sessions.

Conclusion

Product Backlog refinement is a key activity in Scrum that ensures the Product Backlog items are ready for future Sprints. The Product Owner and Developers collaborate during this process to refine, estimate, and prioritize the work. For more information on preparing for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.