Exam Question
During PI Planning, which of the following exposes dependencies between teams that may require coordination?
(choose the best answer)
A. Business Context
B. ART Planning Board
C. PI Planning retrospective
D. Top 10 Features
Correct Answer
B. ART Planning Board
Explanation
Correct Answer
B. ART Planning Board:
This response aligns with SPC principles and SAFe guidance for this situation.
Incorrect Answers
A. Business Context:
This option does not directly relate to the concept emphasized in this SAFe principle.
C. PI Planning retrospective:
This option does not directly relate to the concept emphasized in this SAFe principle.
D. Top 10 Features:
This option does not directly relate to the concept emphasized in this SAFe principle.
Facilitating Effective PI Planning
- SPCs align ARTs on shared goals and objectives during PI Planning.
- Facilitate risk identification and resolution via ROAM.
- Ensure readiness across teams to improve planning outcomes.
Relevance to the SPC Exam
This question format mirrors the actual SPC exam. Understanding the SPC’s role and decision-making logic is essential for passing and for leading transformations.
Key Takeaways
- SPCs guide enterprise-wide Lean-Agile adoption.
- SAFe encourages systemic thinking and long-term enablement.
- Traditional, rigid planning approaches are not effective in SAFe.
Conclusion
Understanding this concept is critical for mastering SAFe roles and passing the SPC exam. For structured practice, visit our SPC Exam Prep.
Read more: