Determining the Number of Product Backlog Items for a Sprint
Understanding who determines the number of Product Backlog items selected for a Sprint is essential for effective Scrum practice. This article explores the roles and responsibilities within a Scrum Team regarding Sprint Planning and the selection of Product Backlog items.
Exam Question
Who determines how many Product Backlog items the Developers select for a Sprint?
(choose the best answer)
A. The Scrum Master.
B. The Product Owner.
C. The Developers.
D. The Scrum Team.
E. The stakeholders attending Sprint Planning.
Correct Answer
C. The Developers.
Explanation
Correct Answer
C. The Developers:
The Developers are the ones doing the work, and they have the best understanding of what can be accomplished during a Sprint. During Sprint Planning, the Developers select the Product Backlog items they believe they can complete to achieve the Sprint Goal.
Incorrect Answers
A. The Scrum Master: The Scrum Master facilitates the Sprint Planning event but does not decide how many items the Developers should select.
B. The Product Owner: The Product Owner presents the ordered Product Backlog items, but the Developers are responsible for selecting the items they will work on.
D. The Scrum Team: While the Scrum Team collaborates, it is specifically the Developers who determine how many items to select.
E. The stakeholders attending Sprint Planning: Stakeholders do not attend Sprint Planning. The event is for the Scrum Team to plan the upcoming Sprint.
Responsibilities in Scrum
- Product Owner: Presents the ordered Product Backlog and ensures it is up-to-date and clear for the Developers to select from during Sprint Planning.
- Scrum Master: Facilitates the Sprint Planning event and helps ensure the Scrum Team adheres to Scrum principles but does not determine the number of items selected.
- Developers: Select the Product Backlog items they will work on during the Sprint and create a plan for delivering a potentially releasable Increment.
Relevance to the PSPO I Exam
Understanding the distinct responsibilities of each role within a Scrum Team, especially during Sprint Planning, is crucial for the PSPO I exam. This knowledge ensures that candidates appreciate the importance of self-management and the collaborative nature of Scrum.
Key Takeaways
- The Developers are responsible for selecting the Product Backlog items for a Sprint.
- The Product Owner provides the ordered Product Backlog for selection.
- The Scrum Master facilitates the process but does not decide on the number of items selected.
Conclusion
In Scrum, the Developers are best positioned to determine how many Product Backlog items they can complete during a Sprint. This self-management is a core principle of Scrum, ensuring that the team works efficiently and effectively to meet the Sprint Goal. For more information on preparing for the PSPO I exam, visit our PSPO I Exam Prep.