Answering: “When is a Sprint over?”

Determining When a Sprint is Over

In Scrum, the conclusion of a Sprint is defined by specific criteria to ensure consistency and predictability in the delivery process. Here is an analysis of when a Sprint is considered over:

Exam Question

When is a Sprint over? (choose the best answer)

  • A. When all Product Backlog items meet their Definition of Done.
  • B. When the timebox expires.
  • C. When the Product Owner says it is done.
  • D. When all the tasks are completed.

Correct Answer

B. When the timebox expires.

Explanation

Why B is Correct

A Sprint is timeboxed, meaning it has a fixed duration that cannot be extended. The Sprint ends when the predefined timebox expires, regardless of whether all the work planned for the Sprint is completed. This approach ensures that the team adheres to a consistent and predictable cadence, which is essential for effective planning and delivery.

Key Points

  • Fixed Duration: Sprints have a fixed timebox (usually 1-4 weeks), and the Sprint ends when this timebox expires.
  • Predictable Cadence: Timeboxing ensures a regular rhythm of work and review, helping teams to improve their planning and estimation skills over time.
  • Review and Adaptation: At the end of the Sprint, the team reviews the work completed, inspects the increment, and adapts their processes in the Sprint Retrospective.

Roles and Responsibilities in Scrum

  • Developers: Work on completing the tasks within the Sprint timebox and ensure that the Definition of Done is met for the Product Backlog items.
  • Scrum Master: Ensures that the team adheres to the timebox and facilitates the Sprint Review and Sprint Retrospective.
  • Product Owner: Reviews the increment at the end of the Sprint and collaborates with the team to plan the next Sprint.

Relevance to the PSM I Exam

Understanding the concept of timeboxing and its role in defining the end of a Sprint is crucial for the PSM I exam. This knowledge helps candidates appreciate the importance of maintaining a consistent Sprint duration and the impact it has on planning and delivery.

Conclusion

A Sprint is over when the timebox expires. This fixed duration ensures that the Scrum Team maintains a consistent and predictable cadence, allowing for regular review and adaptation to improve processes and outcomes.

For comprehensive preparation and practice exams, check out PSM I Exam Prep to enhance your understanding and application of Scrum principles.

Table of Contents

Sign up for more exam tips and discounts



How To Pass PSM I Exam on the First Try
ScrumPrep

PSM I Exam Guide

The Professional Scrum Master I (PSM I) certification is one of the most popular certifications for professionals who want to demonstrate their understanding of the Scrum framework and their ability to apply Scrum in real-world situations. The certification is offered by Scrum.org, a leading global provider of Scrum training and

Read More »

Related Products

LIMITED TIME SALE!
PSM I Practice Tests - ScrumPrep
Power-packed PSM I practice questions and exams will transform your Scrum knowledge and help you pass the PSM I exam easily.
  • 480 PSM Iâ„¢ exam questions
  • Six complete exams with 80 questions each
  • Real exam mode with unlimited question combinations
  • Questions developed by experienced Scrum exam experts
  • Updated to the current PSM Iâ„¢ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here