Answering: “True or False: The Product Owner determines how many Product Backlog items the Developers select for a Sprint.”

Role of the Product Owner in Sprint Planning

Understanding the roles and responsibilities of the Product Owner, Scrum Master, and Developers in Sprint Planning is crucial for effective Scrum implementation.

Exam Question

True or False: The Product Owner determines how many Product Backlog items the Developers select for a Sprint.
(choose the best answer)

  • A. True, accordingly to what was committed to the stakeholders.
  • B. True, but only after confirmation by the resource manager that the Team has enough capacity.
  • C. True.
  • D. False, the Scrum Master does that.
  • E. False.
  • F. False, capacity and commitment are the Project manager’s responsibility.

Correct Answer

E. False.

Explanation

In Scrum, the Product Owner does not determine the number of Product Backlog items the Developers select for a Sprint. The Developers are responsible for selecting the amount of work they believe they can complete during the Sprint based on their capacity and past performance. The Product Owner provides input on the order and importance of the Product Backlog items, but the final selection is up to the Developers.

Why E is Correct

  • Developers’ Responsibility: The Developers are self-managing and determine how much work they can take on in a Sprint based on their capacity and the complexity of the tasks.
  • Collaboration: During Sprint Planning, the Product Owner discusses the goals and priorities, but it is up to the Developers to forecast what they can achieve within the Sprint.
  • Flexibility: This approach allows the team to remain flexible and adapt to changes in scope or unforeseen challenges during the Sprint.
  • Best Forecast: Because the Developers are the ones doing the work, they are the best ones to forecast what they believe they are able to do in order to achieve the Sprint Goal.

Incorrect Options

  • A. True, accordingly to what was committed to the stakeholders: This implies that the Product Owner decides based on stakeholder commitments, which is not aligned with Scrum principles. Developers determine their capacity.
  • B. True, but only after confirmation by the resource manager that the Team has enough capacity: This introduces a role not recognized in Scrum. Developers assess their own capacity.
  • C. True: This is incorrect because it is the Developers who make the decision, not the Product Owner.
  • D. False, the Scrum Master does that: The Scrum Master facilitates the process but does not decide on the work selected.
  • F. False, capacity and commitment are the Project manager’s responsibility: This is incorrect as Scrum does not recognize the role of a Project Manager for these responsibilities.

Responsibilities in Scrum

  • Product Owner: Responsible for maximizing the value of the product and managing the Product Backlog, ensuring it is well-ordered and clearly communicated.
  • Scrum Master: Facilitates Scrum events, helps the team understand Scrum practices, and removes impediments.
  • Developers: Self-managing team members who determine the amount of work they can forecast during a Sprint and work collaboratively to achieve the Sprint Goal.

Relevance to the PSPO I Exam

Understanding the distribution of responsibilities in Scrum is critical for the PSPO I exam. This includes knowing who is accountable for selecting work for a Sprint and how collaboration between the Product Owner, Scrum Master, and Developers is essential for successful Sprint Planning.

Key Takeaways

  • The Developers determine the amount of work they can take on during a Sprint.
  • The Product Owner provides priorities but does not dictate the number of items selected.
  • The Scrum Master facilitates the process but does not decide the workload.
  • Understanding these roles is crucial for effective Scrum implementation and for the PSPO I exam.

Conclusion

In Scrum, the responsibility of selecting the number of Product Backlog items for a Sprint lies with the Developers. This approach ensures that the team remains self-managing and can adapt to the workload based on their capacity and the complexity of tasks. For comprehensive preparation and practice exams, check out PSPO I Exam Prep to enhance your understanding and application of Scrum principles.

Table of Contents

Sign up for more exam tips and discounts



How To Pass PSPO I Exam on the First Try
ScrumPrep

PSPO I Exam Guide

Aspiring Product Owners often find it challenging to pass the Professional Scrum Product Owner (PSPO I) exam. This exam is designed to test your knowledge and understanding of Scrum, Agile, and Product Ownership concepts. The PSPO I certification is an excellent way to validate your understanding of these concepts and enhance your career prospects. In this article, we will discuss the key strategies and tips that you can use to pass the PSPO I exam with flying colors. Table of Contents Understanding the PSPO I Exam Before we dive into the tips and strategies, let’s first understand the PSPO I exam’s format and structure. The PSPO I exam is a 60-minute multiple-choice exam that consists of 80 questions. You need

Read More »

Related Products

LIMITED TIME SALE!
PSPO I Practice Tests - ScrumPrep
Ace the PSPO I exam with our expert-designed practice exams. Boost your knowledge on value creation & delivery, and pass your exam with flying colors.
  • 320 PSPO Iâ„¢ exam sample questions
  • Four complete exams with 80 questions each
  • Real exam mode with unlimited question combinations
  • Questions developed by experienced Scrum exam experts
  • Updated to the current PSPO Iâ„¢ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here