Answering: “True or False: It is mandatory that the product increment be released to production at the end of each Sprint.”

Understanding the Release of Product Increment in Scrum

In Scrum, the release of the product increment is a common point of discussion, particularly in the context of its frequency and timing. This topic is often explored in the PSM I exam to test understanding of Scrum principles.

Exam Question

True or False: It is mandatory that the product increment be released to production at the end of each Sprint.

  • A. True
  • B. False

Correct Answer

B. False

Explanation

Why B is Correct

B. False: The Scrum Guide specifies that an increment must be “Done” at the end of each Sprint, meaning it must be in a usable condition and meet the Definition of Done. However, it is not mandatory for the increment to be released to production at the end of every Sprint. The decision to release an increment is made based on various factors, including business needs, market conditions, and stakeholder requirements. The Product Owner may decide when and if the increment should be released.

Key Points

  • Increment: Each Sprint results in a potentially shippable increment that is thoroughly tested and meets the Definition of Done.
  • Flexibility: While it is possible to release the increment at the end of each Sprint, it is not a compulsory requirement.
  • Product Owner’s Decision: The Product Owner has the final say on whether to release the increment based on the value it brings and the readiness for production.

Responsibilities in Scrum

  • Product Owner: Maximizes the value of the product by ensuring the Product Backlog is well-ordered and refined to the level needed.
  • Scrum Master: Coaches the team in Scrum practices, removes impediments, and facilitates team events to ensure productivity and adherence to Scrum principles.
  • Developers: Collaborate to complete all tasks necessary to deliver a potentially shippable Increment, including ensuring that all Product Backlog items meet the Definition of Done.

Relevance to the PSM I Exam

Understanding the release of product increments is crucial for the PSM I exam. It highlights the flexibility in Scrum and the importance of delivering value while ensuring the increment is ready for production.

Conclusion

In summary, while each Sprint should result in a “Done” increment, it is not mandatory to release the product increment to production at the end of each Sprint. The decision to release is made by the Product Owner based on the context and readiness of the increment.

For comprehensive preparation and practice exams, check out PSM I Exam Prep to enhance your understanding and application of Scrum principles.

Table of Contents

Sign up for more exam tips and discounts



How To Pass PSM I Exam on the First Try
ScrumPrep

PSM I Exam Guide

The Professional Scrum Master I (PSM I) certification is one of the most popular certifications for professionals who want to demonstrate their understanding of the Scrum framework and their ability to apply Scrum in real-world situations. The certification is offered by Scrum.org, a leading global provider of Scrum training and

Read More »

Related Products

LIMITED TIME SALE!
PSM I Practice Tests - ScrumPrep
Power-packed PSM I practice questions and exams will transform your Scrum knowledge and help you pass the PSM I exam easily.
  • 480 PSM Iâ„¢ exam questions
  • Six complete exams with 80 questions each
  • Real exam mode with unlimited question combinations
  • Questions developed by experienced Scrum exam experts
  • Updated to the current PSM Iâ„¢ 2025 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here