Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?”

Handling Incomplete Work in Scrum

In Scrum, it’s essential to adhere to the timebox of the Sprint, which is a fixed period during which the Scrum Team works to achieve the Sprint Goal. Sometimes, despite the best efforts of the team, the planned work for the Sprint cannot be completed. Understanding how to handle such situations is crucial for maintaining the integrity of the Scrum framework.

Exam Question

What happens if the Scrum Team cannot complete its work by the end of the Sprint?
(choose the best answer)
A. The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.
B. The Sprint is extended and future Sprints use this new duration.
C. The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

Correct Answer

C. The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

Explanation

Correct Answer

C. The Sprint length is unchanged and the Scrum Team continuously learns and adapts:
In Scrum, the Sprint timebox is fixed and cannot be extended. If the Scrum Team is unable to complete all the work planned for the Sprint, they review what was completed and what wasn’t during the Sprint Review and Retrospective. The unfinished work is returned to the Product Backlog, and the team learns from the experience to improve future planning and execution. This approach maintains the predictability of the timebox and encourages continuous improvement.

Why the Other Options Are Incorrect

A. The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again:
Extending the Sprint undermines the discipline of timeboxing, which is a core principle of Scrum. The team should adapt and improve within the constraints of the fixed Sprint duration, not by altering it.

B. The Sprint is extended and future Sprints use this new duration:
Similar to the previous option, this approach violates the fixed nature of Sprints in Scrum. Adjusting the duration of future Sprints based on the current one goes against the Scrum framework, which relies on consistent Sprint lengths for predictability and rhythm.

Relevance to the PSD Exam

Understanding how to handle situations where work is not completed within a Sprint is important for the PSD exam. It highlights the importance of adhering to Scrum principles, particularly the concept of a fixed timebox, and emphasizes the value of continuous learning and adaptation.

Key Takeaways

  • Fixed Timebox: The Sprint duration is fixed and should not be extended.
  • Continuous Improvement: The team learns from each Sprint to improve future planning and execution.
  • Product Backlog Management: Unfinished work is moved back to the Product Backlog to be prioritized in future Sprints.

Conclusion

In Scrum, the Sprint timebox remains unchanged regardless of whether all planned work is completed. The Scrum Team continuously learns and adapts to improve their performance in future Sprints. For more information on preparing for the PSD exam, visit our Professional Scrum Developer PSDâ„¢ Exam Prep.

Table of Contents

Sign up for more exam tips and discounts



How To Pass PSD I Exam on the First Try
ScrumPrep

PSD Exam Guide

The Professional Scrum Developer (PSD) exam is an essential certification for anyone interested in developing valuable software using the Scrum framework. The PSD certification is proof of one’s understanding of the principles, practices, and techniques of developing products using Scrum. Passing this exam requires adequate preparation, practice, and dedication. In this article, we will discuss various tips and techniques to help you pass the PSD exam on your first attempt. Table of Contents Understanding the PSD Exam Before diving into the preparation strategies, it’s essential to understand the exam format and content. The PSD exam is a multiple-choice test that consists of 80 questions, and you have 60 minutes to complete it. The questions are designed to test your knowledge

Read More »

Related Products

LIMITED TIME SALE!
PSD Practice Tests - ScrumPrep
Pass the PSD exam with ease using our comprehensive practice exams. Boost your skills in modern engineering practices and become a certified Scrum Developer.
  • 127 PSDâ„¢ exam sample questions
  • Six complete exams with 20 to 27 questions each
  • Real exam mode with unlimited question combinations​
  • Questions developed by experienced Scrum exam experts
  • Updated to the current PSDâ„¢ 2024 exam
  • Pass Guarantee to ensure your success

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here