Exam Question
Which activities will a Product Owner likely engage in during a Sprint?
(choose the best three answers)
A. Gather information and opinions from stakeholders.
B. Prioritize the Developers’ tasks.
C. Run the Daily Scrum.
D. Update the Sprint burndown chart.
E. Answer questions from the Developers about items in the current Sprint.
F. Rearrange Product Backlog items.
Correct Answers
A. Gather information and opinions from stakeholders.
E. Answer questions from the Developers about items in the current Sprint.
F. Rearrange Product Backlog items.
Explanation
Correct Answers
A. Gather information and opinions from stakeholders:
The Product Owner continuously engages with stakeholders to gather information and opinions. This helps ensure that the Product Backlog is well-ordered and that the team is working on the most valuable items. Stakeholder feedback is crucial for refining and ordering the Product Backlog.
E. Answer questions from the Developers about items in the current Sprint:
The Product Owner is available to answer questions from the Developers regarding the items in the current Sprint. This helps clarify requirements, provide additional details, and ensure that the team understands the Product Backlog items they are working on.
F. Rearrange Product Backlog items:
Rearranging Product Backlog items is a key responsibility of the Product Owner. This involves ordering items based on stakeholder input, market changes, and other factors to maximize the product’s value. This activity ensures that the most important work is addressed first.
Incorrect Answers
B. Prioritize the Developers’ tasks:
While the Product Owner orders Product Backlog items, they do not prioritize the Developers’ tasks. Developers are self-managing and decide how best to complete the work within the Sprint.
C. Run the Daily Scrum:
The Daily Scrum is facilitated by the Developers, and the Scrum Master ensures it occurs. The Product Owner does not run this meeting but can attend if they wish.
D. Update the Sprint burndown chart:
Updating the Sprint burndown chart is typically done by the Developers or the Scrum Master if it is used. However, a Sprint burndown chart is not mandatory in Scrum. The focus should be on ensuring progress towards the Sprint Goal.
Responsibilities in Scrum
- Product Owner: Maximizes the value of the product by managing the Product Backlog, engaging with stakeholders, and providing clarity to the Developers. They ensure the Product Backlog is well-ordered and that the team understands the items they are working on.
- Scrum Master: Facilitates Scrum events, helps the team adhere to Scrum principles, and supports the Product Owner and Developers in managing scope and progress.
- Developers: Responsible for turning Product Backlog items into valuable Increments. They manage their tasks, conduct the Daily Scrum, and ensure progress towards the Sprint Goal.
Relevance to the PSPO II Exam
Understanding the key activities of a Product Owner during a Sprint is crucial for the PSPO II exam. It demonstrates knowledge of effective Product Backlog management, stakeholder engagement, and collaboration with the Scrum Team.
Key Takeaways
- The Product Owner gathers information from stakeholders, answers questions from Developers, and rearranges Product Backlog items during a Sprint.
- Developers are responsible for managing their tasks and running the Daily Scrum.
- The Product Owner does not update the Sprint burndown chart or prioritize Developers’ tasks.
Conclusion
The Product Owner plays a vital role in ensuring that the Scrum Team delivers value by managing the Product Backlog and engaging with stakeholders and Developers. For more information on preparing for the PSPO II exam, visit our PSPO II Exam Prep.